Project Portfolio Demonstration · Companion Report 04 of 13

Rocky Mountain Regional VA Medical Center

A plain-language explanation of what the public-record portfolio demonstrates, what CFIG connects, when the decision window existed, and why the alternative decision posture could matter.

Independent public-record demonstrationCFIG did not participate in the projectOutcome-level analysisInternal operating method withheld
EFPS Evidence Guide

How to read and navigate this companion

PUBLIC RECORD

What the cited historical or program record documents.

CFIG ANALYSIS

What CFIG retrospectively connects or would bring forward for decision-makers.

POTENTIAL IMPACT

Source-linked implications for the decisions available at that time.

SOURCE SCOPE

The records reviewed and the decisions they inform.

Interactive Evidence Chain

Select any stage for its supporting detail, or follow the chain from 1 through 9.

Executive Evidence Summary

Cost warnings, incomplete design, complex scope, a changed delivery method, and weak decision controls were connected—not isolated.

This project demonstrates full-life-cycle megaproject warning integration. It shows how CFIG makes separate design, cost, contract, staffing, and schedule warnings visible as one executive decision condition.

Evidence Reviewed

The 82-page VA OIG review, GAO cost-and-schedule testimony, the official facility history, project chronology, findings, and management responses.

What CFIG Discovered

Repeated estimates above budget, evolving and incomplete design, delivery-method change, slow modifications, unclear responsibility, and weak executive controls formed one escalating condition.

Significance

The connected failures affected construction cost, completion timing, contractual leverage, accountability, and delivery of the replacement medical center to veterans and staff.

Decision Window

When contractor and independent estimates showed the evolving design could not be built within the approved $604 million construction amount.

CFIG Response

An early-warning register, change-and-contingency reforecast, and executive responsibility matrix would support a hold, simplify, redesign, fund, delivery-change, or recovery decision.

Exposure Without Action

Design, change, schedule, and accountability gaps could continue compounding while options narrowed, costs increased, and activation moved further into the future.

Executive significance: Makes compounding exposure visible early and supports accountable recovery decisions.
Documented Path

What the portfolio’s public record shows

Recorded project path

Need → Scope and site → Design → Estimate → Contract strategy → Construction → Changes and dispute → Federal recovery and activation.

Evidence boundary

This demonstration uses public audit, accountability, and owner history records. It does not reperform design, cost, legal, or healthcare-facility reviews.

Retrospective CFIG Analysis

What CFIG would bring into one decision picture

Condition CFIG connects

CFIG connected repeated estimates above budget, design complexity, incomplete construction documents, delivery-method change, slow decisions, and unclear accountability into one escalating cost-and-schedule condition.

CFIG-informed path

Source gate → Condition connected → Cost–Schedule–Design Early Warning Register → Change and Contingency Reforecast → Executive Responsibility and Decision Matrix → Should the project hold, simplify, redesign, reforecast, add funding, change delivery, or escalate to recovery management? → Makes compounding exposure visible early and supports accountable recovery decisions.

Decision to be supported: Should the project hold, simplify, redesign, reforecast, add funding, change delivery, or escalate to recovery management?
Decision Window

When meaningful options were still available

When independent estimates first showed the design could not be built within the approved construction amount.

Why timing mattersThe completion estimate moved years beyond the original September 2013 target.
Comparative Differential Analysis

Documented path versus CFIG-informed path

Historical facts and retrospective analysis are separated below. The CFIG column describes what the demonstration indicates CFIG would have surfaced; the source record and proposed decision support remain distinctly identified.

DimensionDocumented project recordCFIG-informed presentationDifferentialLikely impact or benefit
Evidence pictureCost warnings, incomplete design, complex scope, a changed delivery method, and weak decision controls were connected—not isolated.CFIG connected repeated estimates above budget, design complexity, incomplete construction documents, delivery-method change, slow decisions, and unclear accountability into one escalating cost-and-schedule condition.Separate facts become one connected decision condition.Incomplete design, delivery-strategy change, and slow modifications weakened control of price and responsibility.
TimingNeed → Scope and site → Design → Estimate → Contract strategy → Construction → Changes and dispute → Federal recovery and activation.When independent estimates first showed the design could not be built within the approved construction amount.The chronology becomes an explicit window for action.The completion estimate moved years beyond the original September 2013 target.
Decision controlThe public record shows the path taken and the conditions that developed.Should the project hold, simplify, redesign, reforecast, add funding, change delivery, or escalate to recovery management?Historical information becomes a defined leadership choice.Makes compounding exposure visible early and supports accountable recovery decisions.
Risk and valueWork can continue while design and estimate gaps keep creating new changes. Late redesign can stop connected work and move activation years later.Makes compounding exposure visible early and supports accountable recovery decisions.Exposure is weighed against a source-grounded alternative while choices remain.Delay pushed back use of the replacement medical center for veterans and staff.
Potential Impact

Why the differential matters

PROJECT EFFECT

Cost effect

Documented path: The federal record shows the total project estimate grew from $328 million in 2004 to $1.675 billion in the 2016 OIG review, excluding some activation costs. CFIG-informed difference: A unified early-warning register would place each estimate variance beside the related design maturity, scope, funding authority, delivery decision, and accountable executive before additional work advanced. Practical significance: This difference matters because leaders could see that the budget problem was structural—not an isolated estimate—and decide whether to simplify, redesign, reforecast, add funding, or stop further compounding.

PROJECT EFFECT

Time effect

Documented path: The estimated completion moved years beyond the original September 2013 target, and the official history records the later recovery effort and 2018 patient transfers. CFIG-informed difference: The decision record would connect design completeness, unresolved changes, approval latency, schedule impact, and recovery triggers to dated executive decisions. Practical significance: This difference matters because schedule loss becomes an accountable intervention point rather than a downstream consequence discovered after connected work, funding, and activation plans have already moved.

PROJECT EFFECT

Contract effect

Documented path: Incomplete design, a changed delivery strategy, slow modifications, and disputed responsibilities weakened control of price, performance, and contractual leverage. CFIG-informed difference: An executive responsibility matrix would identify who controlled each design, scope, estimate, modification, funding, and delivery decision, what evidence closed the issue, and when escalation was mandatory. Practical significance: This difference matters because unclear ownership lets unresolved conditions migrate into changes and disputes; named authority and closure evidence strengthen timely decisions and the accountability record.

PROJECT EFFECT

Mission effect

Documented path: Delay pushed back use of the replacement medical center for veterans and staff while the project moved through dispute, federal intervention, recovery management, completion, and activation. CFIG-informed difference: The reforecast would connect construction decisions to activation readiness, clinical transition, operational dependencies, and the date the facility could actually serve its mission. Practical significance: This difference matters because the consequence was not only financial; every unresolved project condition also affected when veterans and healthcare personnel could benefit from the replacement facility.

Tangible Options

Three outcome-level choices

These options illustrate the decision support CFIG could provide from the reviewed evidence. CFIG’s operating methods remain proprietary.

OUTCOME-LEVEL OPTION 1

Cost–Schedule–Design Early Warning Register

Decision supportedWhether to hold, simplify, redesign, add funds, or change delivery before more work proceeds.

Potential benefitEarlier control of compounding cost and delay.

OUTCOME-LEVEL OPTION 2

Change and Contingency Reforecast

Decision supportedWhat the real completion forecast is and which changes can still be avoided or sequenced.

Potential benefitMore credible funding and recovery choices.

OUTCOME-LEVEL OPTION 3

Executive Responsibility and Decision Matrix

Decision supportedWho must decide each open issue and when authority transfers.

Potential benefitFaster decisions and a stronger accountability record.

Public Evidence Bridge

Sources supporting the demonstration

The complete coverage notes and exact reliance locations remain in the project portfolio. These links open the original public records.

IDPublic sourceStatusOpen
S1 VA OIG Report 15-03706-33082-page federal review; Findings 1–4, chronology, design phases, and management response. VERIFIED OPEN PUBLIC SOURCE
S2 GAO-14-548TGovernment Accountability Office update on Denver cost, schedule, and scope. VERIFIED OPEN PUBLIC SOURCE
S3 GAO-18-329TGovernment Accountability Office follow-up on cost estimates, schedules, and change-order tracking. VERIFIED OPEN PUBLIC SOURCE
S4 VA Eastern Colorado facility historyOfficial owner history through construction pause, Army Corps recovery, and 2018 patient transfers. SUPPORTING OPEN PUBLIC SOURCE
Completion Boundary

Evidence, decision value, and authority

Decision value: This companion connects cited project evidence to the decisions available at the time, identifies material exposure, and presents outcome-level options for authorized leaders to evaluate.

Professional boundary

CFIG supports decision-makers. Licensed and authorized professionals retain responsibility for engineering, safety, legal, environmental, accounting, regulatory, and other protected judgments.